@thesis{thesis, author={Handayani Oktaria and Sudibyo Uno Bintang}, title ={Tesis dengan Judul STUDI OPTIMALISASI SISTEM KETENAGALISTRIKAN DI BALI BILA TRANSMISI SUTET 500 kV JAWA – BALI CROSSING DIBANGUN}, year={2015}, url={http://156.67.221.169/2111/}, abstract={ABSTRACT With the growth rate of electricity demand in Bali increasing ± 9% per year and in line with the vision and mission of the Bali government called Clean and Green, need a planning system to cope with the demand of electricity needs in Bali. One of the efforts of PT PLN (Persero) as a provider of electric power, according RUPTL 2013-2022 PT PLN (Persero) will build a 500 kV transmission Java - Bali Crossing which is planned to be completed by 2018. By using ETAP 7.0 simulation result is that the construction of the transmission 500 kV Java - Bali Crossing can be a solution to meet the electricity demand in Bali and can reduce the use of fuel generators with voltage value is still within the standard voltage value.} }