@thesis{thesis, author={Rasyid Ridho Muhammad and Sm Hastanto}, title ={ANALISIS PRODUKTIVITAS DAN EFISIENSI PADA PEKERJAAN PENGECORAN PELAT LANTAI, BALOK DAN KOLOM MENGGUNAKAN CONCRETE BUCKET DAN CONCRETE PUMP PADA GEDUNG BERTINGKAT}, year={2020}, url={http://156.67.221.169/3362/}, abstract={Following technological developments, contracting companies or service providers have started to think about the use of efficient and economical construction project implementation methods.The use of heavy equipment and supervision is the most important factor in completing construction project work so that it is on time and has quality according to the standards set. Casting work on the floor slab, beam, and column segments mostly uses ready mix concrete or ready mix concrete. In the process of casting a multi-storey building, you can use a concrete bucket heavy equipment that is assisted by a Tower Crane and a Concrete Pump. Analysis calculation of the cost and productivity calculations on the JHLGallery project, the results for the use of the Concrete Pump tool in terms of productivity have a productivity level of 15.91 m3 / hour, while for Concrete Cuckets of 5.91 m3 / hour. Meanwhile, in terms of the cost of using the tool, the results for the Concrete Pump are Rp. 21,458,764.00 while for the Concrete Bucket which is Rp. 40,238,438.00} }