@thesis{thesis, author={Ikram Carona Bayu and Wirantina K Irma}, title ={ANALISIS PERCEPATAN WAKTU PENYELESAIAN PROYEK DAN OPTIMASI BIAYA DENGAN METODE TIME COST TRADE OFF (Studi Kasus : Proyek Pembangunan Rusunami Dp 0 Rupiah Nuansa Cilangkap, Jakarta Timur)}, year={2021}, url={http://156.67.221.169/4761/}, abstract={In the implementation of construction projects there are often discrepancies between the plan and the realization, such as the occurrence of delays in the process of project implementation. project tethering can occur due to several factors such as design changes, natural conditions and errors in planning. This can result in increased or longer project completion times. Therefore, it is necessary to accelerate the completion time of the project to overcome the delay of the project. In this study will be conducted analysis of the acceleration of the completion time of construction projects in the Rusunami DP 0 Rupiah Nuance Cilangkap East Jakarta Development Project. Where in the implementation of the project there was a delay of the project for 2 months. Therefore, the need to accelerate the completion time of the project to overcome this. In this study used alternative acceleration with the addition of working hours (overtime) with the method of Time Cost Trade Off. The addition of working hours in this pneleitian is 1 hour, 2 hours and 3 hours. The goal in this study is to get the acceleration of time at optimum cost. From the results of the analysis in this study obtained acceleration time with optimum costs, namely by the application of alternative addition of working hours (overtime) 2 hours and obtained a project duration of 618 days with an acceleration of 0.81% of the normal duration and a total cost of Rp. 278.880.146.791 more efficient 0.07% of the normal cost of the project.} }