@thesis{thesis, author={NUGRAHA FIDA ADIGUNA and Sm Hastanto}, title ={ANALISIS PRODUKTIVITAS DAN BIAYA OPERASIONAL TOWER CRANE UNTUK PEKERJAAN STRUKTUR PADA PROYEK PEMBANGUNAN APARTEMEN SKY HOUSE ALAM SUTERA}, year={2021}, url={http://156.67.221.169/4774/}, abstract={Work in construction projects is very complex, in order to be more effective, it takes tools, namely heavy equipment, especially tower cranes. Tower cranes are the main aids used for vertical and horizontal transfer of materials with a range according to their height and radius. Thus, work can be achieved more easily in a relatively shorter time. In this study, it was conducted to take into account the productivity value of tower cranes that contain how the cycle time and production rate of tower cranes, as well as efforts to optimize tower cranes and increase work productivity on projects. Observations were made of one of the crane towers on the silk natural Skyhouse Project which focuses on shearwall work. The goal is to find out the amount of productivity of towercrane which contains the cycle time of tower crane, productivity of work seen from the production of tower cranes, and efforts to make tower cranes work more optimally. From this study obtained the productivity of tower cranes for shearwall work is divided into 3 jobs including shearwall looping is 943 kg / minute., installation of formwork 607.8140 kg / minute, casting work 38.03 kg / minute. And obtained an average productivity value of 106.4061 kg / minute in addition to the operational cost of tower crane of 843,164.00 / hour.} }