@thesis{thesis, author={Aisya Tania Nur and Putri Pratiwi Setyaning}, title ={ANALISIS FAKTOR PENYEBAB KETERLAMBATAN BERBASIS MANAJEMEN RISIKO PADA PELAKSANAANPROYEK RUSUNAMI DP 0 RUPIAH TOWER-A NUANSA CILANGKAP, JAKARTA TIMUR}, year={2021}, url={http://156.67.221.169/4829/}, abstract={Risks is an uncertain event which, if it arises, will have a positive or negative impact on project objectives. The target of this project it self consists of cost, quality and time. The purpose of this study is to identify what are the risk factors that affect time performance, the causes and impacts of dominant risks and what actions and responses are applied to these risk factors in order to minimize delays. In this study, descriptive quantitative methods were used where data collection was carried out by means of surveys through questionnaires and validated by experts for variable determination, questionnaire distribution, validity and reliability testing using SPSS v.26, rangking test analysis and risk levels calculated using Ms. Excel and interviews with respondents for follow-up analysis. The results show that there are 10 types of dominant risk factors that have a higt to moderate category, namely delays in payment of terms, changes in design during the construction process, delays in material delivery, differences in technical specification; drawings of plans and budget plans, delays due to the length of decisions taken or non-approval of the necessary acceleration measures, consecutive losses due to defective materials/workmanship, low worker productivity, inflation and fluctuations, differences in the measurement results of the initial work volume whit actual conditions, and social problems.} }