Abstract :
Construction project activity is an activity that lasts for a limited period of time
and is allocated a certain resource. Construction waste is a waste that will not
increase the value of the final product, waste of materials at the project site,
purchase of excessive materials and excessive labor that can result in waste
construction time. The purpose of these observations to determine a waste of
time(wastetime)on field work on the project as well as to determine the normal
time and standard time standard based onwork. value stream mapping. Factors
wasting time (waste time) in column work can be caused by workers and
equipment. Meanwhile, the standard time to carry out the actual work is
obtained from the calculation, namely the column work is about 921 minutes
assuming 8 hours of work time per day, the normal implementation of column
work is 2 days. The wastage of time (waste time) obtained based on the value
stream mapping on column work was 18%.