Abstract :
Aramco or better known as corrugated pipe is a work method that is rarely used/practiced during
bridge construction and made the author to adopt this work method which aims as learning material
when carrying out bridge work. This work method does not take long because the corrugated pipe is
ordered directly (no special installation is required) and the soil is used from the rest of the
reclamation area. The use of this type of corrugated pipe work method can be the right alternative
for construction management. The existence of a project error factor in terms of time makes engineers
and project implementers make changes so that the execution time of the work is in accordance with
the plan. For corrugated pipe work based on the calculation of work time it takes 7 working days 1
hour. The target time for the 5 PIK 2 bridge work for 9 months 2 weeks with reference to the
realization of the work and this corrugated pipe work will affect the erection girder work in
realization it takes time 4 days and using aramco for this superstructure work takes 4 working days.
In the factors that affect work time, the top 5 rankings are carried out for implementation and impact
for bridge projects.