Abstract :
Developments in the construction industry in Indonesia continue to
grow every year causing more and more construction companies in Indonesia to
be able to win the competition. Therefore, construction planners also continue
to make developments on the method of implementing a construction.
Developments in the method of implementing a construction are aimed at
achieving the most economical possible cost and high quality in order to be
competitive by reducing the duration of execution time, and also reducing the
amount of labor used.
In this study, a comparison of conventional floor and work methods will
be carried half slab in the Apartment Development Project Tokyo Riverside out
in terms of time and cost. In this study, the cost analysis refers to SNI ? 7832 ?
2017 and analysis of calculations from data in the field.
The results of a comparative analysis of two working methods half slab
of conventional and obtained results for method the half slab execution takes
55.57 days at a cost of Rp5.816.499.551 whereas conventional implementation
takes 58.34 days and cost Rp7.989.274.360.