ANALISIS WAKTU DAN BIAYA PENYELESAIAN PROYEK APARTEMEN SKYHOUSE ALAM SUTERA MENGGUNAKAN METODE CRASHING DENGAN PENGATURAN SHIFT TENAGA KERJA
Total View This Week0
Institusion
Institut Teknologi Perusahaan Listrik Negara
Author
AMALIA, TRIA NUR
D Siswoyo, Sriyono
Subject
Teknik Sipil 
Datestamp
2022-09-20 04:01:20 
Abstract :
Project delays will cause an increase in labor costs and equipment costs, although it does not result in an increase in the volume of work but can increase material prices, this can occur due to the lack of optimal control methods in the field. Projects that experience delays can be overcome by the method of acceleration (crashing) by setting shifts labor. This research was conducted at the Alam Sutera Skyhouse Apartment Project. Analysis of duration acceleration is carried out on work that is on a critical path withsettings shift. Calculation of material requirements and wages during shifts is carried out using the 2016 Unit Price Analysis guidelines. After analyzing the calculations on the work to be accelerated,duration will be obtained shift the requiredaccording to the volume reviewed and the changes in costs can be calculated. After accelerating shif methodt, the project can be accelerated for 12 working days so that the project duration from 972 working days becomes 960 working days. Direct costs have increased from Rp. 148.750.000.000,- to Rp. 149.467.054,242,-. Indirect costs decreased from Rp.26.250.000.000,- to Rp. 26.114.975.308,64,-. However, due to accelerated work on only 3 floors, indirect cost did not giving a large decrease, not proportional to the increase in direct costs , this resulted in the total project cost increasing by a difference of Rp. 612.378.764,36,- from normal project. 
Institution Info

Institut Teknologi Perusahaan Listrik Negara