Abstract :
The final project entitled "Analysis of the Difference in Unit Price of Pile Cap Casting
Work Units Between the Actual Method and SNI for the 150 kV High Voltage Airway
Construction Project in Teluk Naga" aims to determine the price of pile cap casting work
every 1m3between the actual conditions in the field and SNI which is an analysis Work
Unit Prices which have been stated in the PUPR Ministerial Regulation No. 28 of 2016.
The data collection method used is direct observation in the field, collecting daily work
report data and unit price data, then the results will be compared with comparative
analysis. The results obtained in this study are the unit price of pile cap casting work
every 1 m3 on the construction project of the 150 kV high voltage overhead line Teluk
Naga with the actual method is 1,304,076.97 rupiah, while using SNI is 1,550,644.20
rupiah. . The percentage difference is that the actual method is 15.90% cheaper than SNI,
or the difference is 246,567.23 rupiahs.