Abstract :
ABSTRAK
PRARANCANGAN PABRIK PARALDEHIDA
DARI ASETALDEHIDA DENGAN KATALIS ASAM SULFAT DAN ASAM FOSFAT
KAPASITAS 21.000 TON/TAHUN
(Perancangan Reaktor (RE-201))
Oleh
ANDANI DIAH ARUM SAVITRI
Pabrik paraldehida berbahan baku asetaldehida, akan didirikan di Kawasan Industri Gresik, Gresik, Jawa Timur. Pabrik ini berdiri dengan mempertimbangkan ketersediaan bahan baku, sarana transportasi yang memadai, tenaga kerja yang mudah didapatkan dan kondisi lingkungan.
Pabrik direncanakan memproduksi paraldehida sebanyak 21.000 ton/tahun, dengan waktu operasi 24 jam/hari, 330 hari/tahun. Bahan baku yang digunakan adalah asetaldehida sebanyak 2810,69 kg/jam, katalis asam sulfat sebanyak 5,62 kg/jam dan asam fosfat sebanyak 11,24 kg/jam.
Jumlah karyawan sebanyak 132 orang dengan bentuk perusahaan adalah Perseroan Terbatas (PT) menggunakan struktur organisasi line dan staff.
Dari analisis ekonomi diperoleh:
Fixed Capital Investment (FCI) = Rp 810.504.088.778,-
Working Capital Investment (WCI) = Rp 143.030.133.314,-
Total Capital Investment (TCI) = Rp 953.534.222.092,-
Break Even Point (BEP) = 55%
Shut Down Point (SDP) = 25,97%
Pay Out Time after Taxes (POT)a = 2,64 tahun
Return on Investment after Taxes (ROI)a = 23,64 %
Internal Rate Return (IRR) = 30,7%
Annual Net Profit (Pa) = Rp 258.239.203.406/tahun
Mempertimbangkan paparan di atas, sudah selayaknya pendirian pabrik paraldehida ini dikaji lebih lanjut, karena merupakan pabrik yang menguntungkan dan mempunyai masa depan yang baik.
ABSTRACT
PRADESIGN OF PARALDEHYDE PLANT
FROM ACETALDEHYDE WITH SULFONIC ACID AND PHOSPORIC ACID
CAPACITY 21.000 TONS/YEAR
(Design Reactor (RE-201))
By
ANDANI DIAH ARUM SAVITRI
A plant to produce paraldehyde from acetaldehyde is planned to be located at Kawasan Industri Gresik, Gresik, East Java. The plant is established by considering availability of raw materials, transportation facilities, readily available labor and environmental conditions.
Capacity of the plant is 21.000 tons/year operating 24 hour/day and 330 working days/ year. The plant required 2810,69 kg/hr acetaldehyde, 5,62 kg/hr sulfonic acid, and 11,24 kg/hr phosporic acid.
Quantity of labor is around 132 people. The plant is managed as a Limited Liability Company (PT), which is headed by a Director who is assisted by a Director of Production and Director of Finance. The company is organized in the form of line and staff structure. From analysis of the plant economy is obtained:
Fixed Capital Investment (FCI) = Rp 810.504.088.778,-
Working Capital Investment (WCI) = Rp 143.030.133.314,-
Total Capital Investment (TCI) = Rp 953.534.222.092,-
Break Even Point (BEP) = 55%
Shut Down Point (SDP) = 25,97%
Pay Out Time after Taxes (POT)a = 2,64 tahun
Return on Investment after Taxes (ROI)a = 23,64 %
Internal Rate Return (IRR) = 30,7%
Annual Net Profit (Pa) = Rp 258.239.203.406/tahun
By considering above the summary, it is suitable study further the paraldehyde plant since plant is profitable and has good prospects.