Abstract :
The development of the corporate world industry tinged with an
increasingly tight competition. To win the competition, every company must have
been required to do the planning and control of production as possible in making a
particular product. This includes planning and controlling how the company was
able to cultivate resources which are owned, such as labor, capital, machinery,
raw materials and working methods as well as to generate optimal production
numbers with fixed amount of attention to customer requests. In addition to
generating the optimal production quantities, the company must also pay attention
to the capacity of the company's resources, such as raw materials, so that isn't the
case surplus or shortage of raw materials which cause harm to the company, as
well as trying to deliver products in a quick and precise.
CV Emwe Rona Jaya is one of the companies that engaged in furniture that
focus is producing cabinets. In the daily activities of companies producing
wardrobes in accordance with orders coming from the consumer. The problems
faced by companies today that there is an imbalance between consumer demand
and the existing workforce and production number of the closet so it imposes on
product availability.
The problem of evaluation planning between requests, whether the need for
additional manpower to fullfill the request production capacity of the cabinets
using Rought Cut Capacity Planning (RCCP).
Rought Cut Capacity Planning is "analysis to test the availability of the capacity
of the production facilities available in the master production schedule meet
(Master Production Schedule) that has been established with engineering Bill Of
Labor (BOL)".
Of research results, by performing calculations and forecasting capacity
planning (RCCP) production to meet consumer demand can be deduced that the
Master Production Scheduling experience increased, initially as many as 153 units
after the foreseen increase of as much as 165 units with an increase of 8.07%.
From these results it is known that the work process measurement, cutting,
polishing, assembling and finishing products already meet the needs of production
capacity. Because the time available is greater than capacity needs, the company
does not require additional overtime hours, machines and labor.
Keywords: Capacity, Master Production Schedule (MPS), rought Cut Capacity