Abstract :
Industrial development of increasingly advanced, indirectly spur the owners
of the company to continue to expand the existing track. Every company is trying to
meet consumer demand in order not to lose customers utama.Proses effective and
efficient production is something to be achieved every manufacturing company today.
Time becomes very influential in a production (makespan).
PT. PAL INDONESIA is a shipbuilding company whose main activities are
producing warships, merchant ships, and ship fast (special vessels). Ship - ship
production PT. PAL INDONESIA (Persero) has served in the waters around the
world. In the process of operational PT. PAL Indonesia has not made optimal
production scheduling, this situation is the lack of clarity led to the work done in each
lane.
The purpose of this study is in the process of operational PT. PAL Indonesia
has been no production scheduling in each lane, this situation is the lack of clarity led
to the works. Therefore, researchers wanted to help the company in Job shop
scheduling with priority dispatching rule heuristic approach, hoping to clarify the
process of being made.
Based on the results of data processing, the method Heuristic Priority
Dispatching Rule Short Processing Time (SPT) at 117.67 makespan obtained by
order of the process is the product size 150A - 200A - 100A - 80A - 125A - 65A,
while Long Processing Time (LPT) product completion time (makespan) amounted to
117.411 hours of the order process is the size of 65A - 125A - 80A - 100A - 200A -
150A.
Keywords
: Group Technology, Production Scheduling, Dispatching Rule Priority
Heuristic methods, SPT, LPT, makespan