Abstract :
In a production activity, to obtain an optimum result, all activities should
be planned first production well, one of which is by way of scheduling or
scheduling. Scheduling and work order in a job (job) is very important, with the
scheduling assignment attempted to get a job on the machine, so there is no
accumulation of job done on one machine simultaneously.
PT. Tjokro Putra Perkasa is a company engaged in the manufacturing
industry. Which manufactures mechanical parts based on order (job order) with
various types. Problems faced by the company during this time was a delay in the
completion of a product. This is because the company has been implementing the
FCFS job scheduling system on a first come first served. In meeting the demand
of consumers is less efficient because there are still some jobs that can not be
completed within the time desired by the buyer (customer).
The purpose of this research is to determine the proper gear production
scheduling so as to minimize the makespan by using CDS (Campbell Dudeck
Smith), Palmer and Dannenbring.
The method of calculation turns out the actual company produces
makespan scheduling for 317707 seconds. Several methods of production
scheduling is proposed CDS method (Campbell Dudeck Smith) produces
makespan 312213 seconds, Palmer method produces makespan 315437 seconds
and Dannenbring method produces makespan 315437 seconds. By applying the
proposed method, selected (Dudeck Campbell Smith), the production turnaround
time is quicker with time savings of 5494 seconds
?
1.5 hours (or about 1.73%).
Keywords:
CDS, Palmer, Dannenbring, Job, Scheduling.