Institusion
Universitas Bung Hatta
Author
Neneng, Rahtu Sumantri
Martalius, Peli
Vivi, Ariani
Subject
TH Building construction
Datestamp
2023-08-11 03:27:28
Abstract :
This paper aims to be able to analyze the construction work on The Manor Office Tower.The Manor
Office Tower Project is located on Jl. Surya Utama Kav C1, Suryacipta Ciampel Industrial Area,
Karawang, West Java. The Manor Office Tower consists of 8 floors and 2 roofs with a building area
of ± 11,264 m². Projects with contracts of Rp 67,643,871,638.- with preliminary work, structural
work, architectural work, mechanical and electrical work, and occupational drainage work for 23
calendar months. The calculation results of the upper structure estimate covering the work of
columns, beams, slabs, shear walls and stairs project cost The Manor Office Tower Rp
25.075.088.244.- using the Work Unit Price Analysis of Indonesian National Standard in 2013. Total
cost includes VAT10%. For each of structure work are column is Rp 4,047,153,118, shear wall is Rp
1.865.887.451, beam is Rp 6,055,758,220, slab is Rp 10.258.030.308 and stair is Rp
568.705.671.Based on the time schedule of the structural work of The Manor Office Tower Project.
Which made the top structural work completed for 46 weeks. Advances received at the beginning of
the project amounted to 10% of the project value. To achieve the target of construction project in
accordance with the schedule, then in the construction project should pay attention to quality control
items, among others: material schedule, man power schedule and time and wage work. These three
components play a role in the preparation of BOQ, one and the other are related and if one
experiences delays or increases in cost.It is almost certain that it will directly affect other items, and
ultimately result in delays and increases in the total cost of construction projects.
Keywords:
Bill Of Quantity, Cost Analysis, Time Schedule, S Curve, Cash Flow, The Manor Office Tower